BREEAM Wst01:
Construction Waste Management

BREEAM Wst01 rewards contractors for minimising construction waste sent to landfill. This guide covers credit levels, diversion rate targets, what evidence your assessor needs, and how to build a compliant movement register from day one.

Credit levels and diversion rate targets

1 Credit

70% diversion from landfill

Site Waste Management Plan (SWMP) prepared pre-construction
At least 70% of total waste diverted from landfill by weight
Digital movement register for all waste streams
Evidence of carrier licence verification for all collections

2 Credits

80% diversion from landfill

All requirements for 1 credit
At least 80% of total waste diverted from landfill by weight
Waste stream breakdown by EWC code
Destination facility details for each movement

3 Credits

95% diversion from landfill

All requirements for 2 credits
At least 95% of total waste diverted from landfill by weight
Complete movement register from groundworks to practical completion
Assessor-ready evidence pack with signed carrier confirmations

What counts as diverted waste?

✓ Counts as diverted

Recycled (MRF)

Composted

Energy from Waste (EfW)

Reused on site

Reused off site

Inert material to appropriate facility

✗ Does not count

Standard landfill

Hazardous waste landfill

Unknown disposal route

Unverified carrier movements

Movements without destination records

Evidence your assessor needs

Every item below must be present in your submission. Missing any single element is grounds for rejection regardless of the diversion rate achieved.

1Completed Site Waste Management Plan (SWMP) dated pre-construction
2Digital waste movement register — every collection from site start to PC
3Waste quantities by type and EWC code (kg or tonnes)
4Disposal route for each movement (landfill, recycled, reused, composted, energy recovery)
5Carrier name and EA upper-tier waste carrier registration number for each collection
6Receiving facility name and address for each movement
7Diversion rate calculation — total non-landfill tonnes ÷ total waste tonnes × 100
8Signed declaration from the principal contractor

Frequently asked questions

What is BREEAM Wst01?

BREEAM Wst01 is the Construction Waste Management credit within the BREEAM UK New Construction and Refurbishment rating schemes. It awards up to 3 credits for managing construction waste responsibly — primarily measured by the percentage of waste diverted from landfill. A SWMP and a complete digital movement register are mandatory evidence requirements for any credit level.

What counts as waste diversion from landfill?

Any disposal route other than landfill counts as diverted. This includes: recycling (MRF), composting, energy from waste (EfW), reuse on site, reuse off site, and inert fill. Inert landfill (soil, concrete, bricks) counts towards the diversion rate if diverted to an appropriate facility. Standard landfill and hazardous waste landfill do not count.

Is the 95% diversion rate achievable on a typical new-build?

Yes — modern construction sites regularly achieve 95%+ diversion with the right skip segregation and carrier selection. The key is actively choosing recycling and energy recovery routes from the start of the project, separating inert materials (concrete, soil, bricks) from mixed construction waste, and logging every movement so nothing is counted as landfill by default.

When does the SWMP need to be prepared?

The Site Waste Management Plan must be dated before construction work begins (pre-construction). A SWMP produced retrospectively will not be accepted by a BREEAM assessor regardless of the diversion rate achieved. WasteMapper prompts you to complete the SWMP fields at project creation.

Who needs to verify carrier licences for Wst01?

The principal contractor is responsible for verifying that every waste carrier used on site holds a valid Environment Agency upper-tier waste carrier registration. This must be documented in the movement register — the licence number, carrier name, and registration status at the time of collection. WasteMapper verifies licences live against the EA register at the point of logging.

Can WasteMapper generate the Wst01 evidence pack?

Yes. WasteMapper compiles the full Wst01 evidence pack in one click — movement register, diversion rate calculation, carrier verification log, waste stream breakdown by EWC code, and a formatted PDF ready for submission to your BREEAM assessor. Available on Site, Pro, and Intelligence plans.

Does BREEAM Wst01 apply to refurbishment projects?

Yes. BREEAM Refurbishment and Fit-Out includes a Wst01 equivalent credit with the same evidence requirements. The diversion rate targets may differ slightly by scheme version — check with your assessor for the applicable version of BREEAM on your project.

Generate your Wst01 evidence pack in one click

WasteMapper logs every movement, verifies every carrier, and compiles the complete assessor-ready evidence pack automatically. Free plan available.

Start free Download SWMP template

Related resources

Digital Waste Tracking 2026 SWMP template Waste cost calculator